Step 1 Clear

Sweep the base of the pothole of any loose debris by sweeping or raking. Ensure that no large loose rocks are present in the pothole before pothole repair step 2.

Step 2 Pour

Fill the pothole with Go Green Cold Asphalt Patch. Recommended compacted depth is 50mm. If area is deeper than 50mm, compact in layers (no deeper than 50mm per layer).

Step 3 Tamp

When hole is filled, apply a small crown to repair area to allow for additional compaction. Now tamp, or wheel roll for the final time , and you may now open to traffic – immediately!! It’s that simple. 